CMC-EIMS · Recommended Solution 02Production Readiness Solution Proposal

Production is decided
before it begins

From automated MPS and MRP through E-MPS and CRP, and on to APS

To answer an order with “We can deliver by when?”, schedules, materials, people, and equipment must be viewed within a single plan. CMC TECH explains the structure of its proprietary production readiness solution and the sequence in which it expands.

MPS→E-MPS→MRP→CRP→APS
CMC TECH · CMC TECH2026
CMC-EIMS · Production Readiness01 · Starting Point

“This order—by when can we deliver it?”

The reason it is difficult to answer this customer question immediately is not the ability of the person in charge, but where the information is located.

Sales asks production,
production asks materials,
and materials asks suppliers.

While the answer is making its way back, another order arrives and the conditions change again. As a result, delivery-date responses are delayed, and promises made in haste come back as adjustments on the day of production.

CAPACITYCapacityHow much capacity is available on the lines and in the processes during that period?
MATERIALMaterialsWill the required parts arrive before the input date?
WORKFORCEPeopleAre the personnel and shifts needed to handle the process secured?
EQUIPMENTEquipmentCan it operate after excluding repair and calibration schedules?
The four answers are in different places. Excel, the person in charge's memory, the warehouse, and the equipment register. This proposal covers the sequence for bringing all four together into a single plan.
CMC TECH · From Automated MPS and MRP to APS02 / 18
CMC-EIMS · Production Readiness02 · Diagnosis

The problem becomes visible on the day of production,
but the cause lies in the preparation stage.

Even when MES records actual results accurately, the burden on the shop floor remains if preparation is insufficient. Here are eight recurring shop-floor symptoms and their causes.

Symptoms visible on the shop floorCauses in the preparation stageRelevant functions
ScheduleThe schedule slips on the day, even though production started as plannedA schedule that does not reflect the line’s daily capacity and working daysMPS capacity-based allocation
The same semi-finished product is made over several daysOrders are issued separately for each finished product, so common demand cannot be consolidatedMPS hierarchical planning
It is risky to change the conditions and recalculateThe calculation results are immediately reflected in actual production ordersSeparation of planning and ordering
It is impossible to tell which process is causing the bottleneckThere is only a product-level plan, with no process-level scheduleE-MPS process-level planning
MaterialsThe shortage is discovered only after the line stopsThe point at which a shortage will occur is not calculated in advanceMRP time-phased planning
Materials are purchased again even though they are already in stockOn-hand inventory and purchase orders already placed cannot be included in the calculationMRP net requirements calculation
Recalculation removes purchase orders that have already been organizedThere is no distinction between confirmed purchase orders and purchase orders under reviewConfirmed boundary · Fixed purchase orders
The materials are ready, but there are no people or equipmentOnly materials are prepared, without reviewing capacityCRP · APS
CMC TECH · From Automated MPS and MRP to APS03 / 18
CMC-EIMS · Production Readiness03 · Structure

Five questions, One plan

CMC-EIMS expands production preparation across five stages. Start with the stages you need and expand to the next stage using the same master data.

STEP 1MPSMaster Production ScheduleWhat to make, when, and how muchConvert orders into an executable schedule and issue production orders only for confirmed plans
STEP 2E-MPSExtended master production scheduleWhich process, and whenBreak down the product-level plan into process-level schedules and process sequences
STEP 3MRPMaterial Requirements PlanningWhat to purchase, when, and how muchCalculate shortage dates and purchase orders by exploding the BOM and reflecting inventory and existing purchase orders
STEP 4CRPCapacity requirements planningDo we have the capacity to do the workCompare the planned workload with the available time of equipment and personnel
STEP 5APSAdvanced planning and schedulingCan we meet the delivery dateAssess delivery feasibility by reviewing capacity, materials, personnel, and equipment simultaneously
Common master dataItems · BOMs · processes (routings) · resource capacity · factory calendars · lead times · lot policies — all five stages use the same master data.
↺MES actuals · work in process · lossesReturn to this plan to refine the next plan. Planning and execution are not completed in a single pass; they are repeatedly aligned.
CMC TECH · From Automated MPS and MRP to APS04 / 18
CMC-EIMS · Production Readiness04 · MPS ①

The status of a single order
Seven stagesare managed

You do not need to open multiple screens to check whether an order has been planned, an order has been issued, or a confirmation has been recorded. The workflow menu always displays the current stage.

Order
Planning
Plan confirmationCurrent stage
Issue order
Confirmation
Production
Completed
Previous stageReview the resultsSelect it to go directly to the planned order and production order generated at that time.
Current stageExecute the taskThe relevant task screen opens with the item and quantity for that demand already populated.
Subsequent stageRestrict executionStages that have not yet been reached cannot be executed, and the prerequisite tasks are indicated.
  • No need to enter the same values againThe order’s item number, quantity, and due date carry over to the plan creation screen.
  • Production not included in orders, within the same planRegister inventory replenishment, trial production, rework, and urgent orders through the five-stage entry process.

This is not a menu for skipping stages. If the plan has not been confirmed, complete the prerequisite tasks first. During implementation, the approval procedures for plan changes and shop-floor changes are configured to match your operating standards.

CMC TECH · From Automated MPS and MRP to APS05 / 18
CMC-EIMS · Production Readiness05 · MPS ②

Not a schedule on paper
An executable scheduleis calculated

Simply distributing production quantities across dates does not show whether the schedule is feasible on the shop floor. Resource capacity and the factory calendar provide the basis for the schedule.

  • Allocate within capacity limitsAllocate work while observing the daily capacity and working days of lines and equipment. No work is scheduled on non-working days.
  • Highlight overloaded periods with colorDistinguish utilization of 85% or more from utilization exceeding 100% by resource and date.
  • Show the basis for the calculationShow setup and processing times, whether there is a delay, and the demand fulfilled by this order.
  • Recalculate immediately when movedWhen a bar is moved, the planned order and resource load are recalculated, and other orders that should be reviewed together are indicated.
MonTueWedThuFriSatDayMonTueWedThuFriSMT Line 172%80%88%96%104%ClosedClosed92%78%70%64%60%SMT Line 240%55%60%72%84%ClosedClosed90%86%74%66%58%Assembly Line60%62%70%78%86%ClosedClosed112%98%82%70%64%Functional Testing50%54%58%66%72%ClosedClosed88%94%80%68%60%Capacity Buffer85% or higherOver 100% — Review schedule adjustment or capacity expansion
Daily load by resource — SMT Line 1 on Friday and the assembly line on the following Monday exceed capacity.Illustrative Example

Even when calculations reflect capacity, any indication of overload or delay requires checking the cause and input conditions. This does not mean that delivery dates are guaranteed under any circumstances.

CMC TECH · From Automated MPS and MRP to APS06 / 18
CMC-EIMS · Production Readiness06 · MPS ③

Common subassemblies are in one batch,
recalculated safely

Electronic products often have multiple models sharing the same PCB ASSY. Both consolidating demand and repeating calculations must be possible without adding unnecessary burden.

Plan finished goods and subassemblies separately, then consolidate demand

Black Box 1-Channel1,000 units · Starts Monday
Black Box 2-Channel600 units · Starts Wednesday
→
Common PCB ASSY: 1,600 unitsProduced with a single setup
If instructed separately, the 1,000 and 600 units require two setups and two product changeovers
Confirm which finished product the quantity is for in the hierarchy.Illustrative Example

Plans and instructions are separated

PLANPlanningRun calculations multiple times with different conditions. The preview does not create a planning version, so no data remains after you close it, even after reviewing it.
Confirmed
ORDERProduction OrderAn order number is assigned only when the order is confirmed. After that, manage confirmation, completed quantities, and change-request status.
  • Show the reason when requested and planned quantities differIndicate which policy was applied: yield, minimum lot size, or multiples.
  • Count items requiring actionCapacity overload, start-date overrun, or unscheduled items.
CMC TECH · From Automated MPS and MRP to APS07 / 18
CMC-EIMS · Production Readiness07 · E-MPS

E-MPS — Extends product planning
process planninginto

Extended MPS goes beyond finished-good quantities and completion dates to plan schedules for each process, along with the equipment and personnel required for those processes.

Day 1Day 2Day 3Day 4Day 5Day 6Day 7Day 8Day 9Day 10Delivery DeadlineMPS · Product LevelBlack Box 1-Channel, 1,000 units — A single bar cannot show which process is causing the bottleneckE-MPS · Process LevelSMTSMT Line 1 · 2 peopleInsertion · Wave SolderingWave Soldering Machine 1 · 3 peopleAssemblyAssembly Line · 6 peopleBottleneck · 112% loadFunctional Testing2 inspection jigs · 2 peoplePackagingPacking Station · 2 people
Expanding the plan by process reveals that the assembly process is causing the load to exceed the delivery deadline.Illustrative Example

Four Things E-MPS Adds

  • Schedules and dependencies by processCompletion of the preceding process becomes the condition for starting the next process.
  • Equipment Availability ConditionsReflect the available operating hours of the equipment assigned to each process.
  • WorkforceReview the personnel required for each process together with shift conditions.
  • Interprocess Waiting and Work in ProcessCheck not only processing time but also the lead time that accumulates between processes.

The longer and more equipment-dependent the processes are, as in SMT, the harder it is to identify bottlenecks through product-level planning alone. The scope of connections among processes, equipment, and personnel is confirmed for each customer before finalization.

CMC TECH · From Automated MPS and MRP to APS08 / 18
CMC-EIMS · Production Readiness08 · MRP ①

From Production Planning to Purchase Orders
Five Steps

Once MPS determines what to make and when, MRP calculates the materials required for production and when they are needed. The starting point is a confirmed production order.

Confirm DemandBring in confirmed production orders and check what to make, when, and in what quantity
CalculateExpand the BOM level by level to calculate the required quantities of subassemblies and components
Review MaterialsSubtract inventory and existing orders, leaving only the actual shortages
Prepare OrdersSelect the items to purchase and adjust quantities and dates
Issue Purchase OrdersGroup items by supplier, create purchase documents, and send them to the purchase order screen

Your tasks are divided into three cards

NOWTo Order NowCount and Amount
CHECKItems requiring confirmationDelayed receipts, new demand
NEXTWhat to review nextReview in a later cycle

Prioritize urgent items by when shortages will occur

Already shortImmediate actionFind alternatives · Expedite sourcing
Within 2 weeksFinalize purchase orderConfirm lead time
Within 4 weeksScheduled for reviewMonitor demand fluctuations

Do not place an order based on color alone. Confirm the supporting evidence—whether an existing receipt was delayed or new demand has arisen—before making a decision.

CMC TECH · From Automated MPS and MRP to APS09 / 18
CMC-EIMS · Production Readiness09 · MRP ②

How muchrather than
when it will be shortis calculated

A large gross requirement does not mean purchasing the entire quantity. We reflect the quantity already secured and distinguish the week when a shortage will occur from the week when an order must be placed.

Connector C-100Week 1Week 2Week 3Week 4Week 5Week 6
Gross requirement3004000600300400
Scheduled receipt (already ordered)05000000
Net requirement000500300200
Planned receipt000500500500
Planned order050050050000
Projected inventory200300300200400500

On-hand inventory 500 · Safety stock 200 · Lead time 2 weeks · Order multiple 500Illustrative Example

The gross requirement is 2,000 units, and the quantity to be newly ordered is 1,500 units. And the first order must be placed not in Week 4, when the shortage occurs, but in Week 2.

Trace back why this quantity is needed

Connector C-100 · 600 unitsNeeded in Week 4
→
PCB ASSY · 600 unitsSubassembly plan
→
Black box, 2-channel · 600 unitsProduction orders and sales orders

Tracing the basis of requirements (pegging) provides the rationale for quantities in purchase approvals and is the starting point for identifying materials affected when demand changes.

CMC TECH · From Automated MPS and MRP to APS10 / 18
CMC-EIMS · Production Readiness10 · MRP ③

Even when recalculated
the plans already made do not disappear

If even purchase orders agreed upon through consultation fluctuate with every recalculation, the person in charge has to repeat the same work. Fixed orders and the firm zone define that boundary.

Firm zone · Default 14 days (changeable)Recalculation rangeTodayWeek 1Week 2Week 3Week 4Week 5Week 6Orders within the firm zoneRemain unchanged after recalculationFixed orderQuantity, date, and supplier retainedPlanned orderRecalculate when conditions change
Orders that have been issued are calculated as scheduled receipts, while inherited fixed plans are calculated as secured quantities, so the same quantity is not counted twice.Illustrative Example
When a receipt arriveswe only reread the inventoryOnly projected inventory and the timing of shortages are updated. Planned orders and fixed orders remain unchanged.
Each time it is calculatedstored as a cycleThe conditions and results at that point are retained, allowing you to review why a previous plan was made.
Two cycles side by sideCompare only what has changedClassify changes as newly added, increased, decreased, or rescheduled.

If demand or the BOM itself has changed, you must check whether an inventory update alone is sufficient. Preserve the cycle that served as the basis for the order and review the new conditions as a new cycle.

CMC TECH · From Automated MPS and MRP to APS11 / 18
CMC-EIMS · Production Readiness11 · CRP

CRP — Even when materials are ready
the capacity to executeis still required

Capacity requirements planning compares planned workloads with available capacity using the same time unit. Knowing in advance which weeks are over capacity gives you more options for responding.

0h50h100h150h200h118hWeek 1142hWeek 2+16h over capacityWeek 3+8h over capacityWeek 4150hWeek 5124hWeek 6Available capacity 160h / weekPlanned work hours for the SMT process · 2 lines · based on a 5-day workweek
Capacity is exceeded in Weeks 3 and 4. This is identified during the planning stage, not on the production day.Illustrative Example

Three components of capacity

  • EquipmentAvailable operating hours, repair and calibration schedules
  • PeopleWork rules, shifts, actual attendance, and available personnel
  • ProcessesStandard time, setup time, and yield

Responses to overcapacity

RescheduleDistribute across weeks with spare capacity
Additional shifts · OvertimeExpand available hours
Split lotsStart with the quantities first
Review subcontractingOutsource by process

People’s time is also a production resource. When connecting it to work standards in HR and time and attendance, define personal data access and approval responsibilities in line with company rules.

CMC TECH · From Automated MPS and MRP to APS12 / 18
CMC-EIMS · Production Readiness12 · APS

APS — four resources View them at once
Assess delivery feasibility

Select an order and run a simulation to evaluate capacity, materials, people, and equipment together. Before confirming it, first identify what needs to be addressed.

OrderSelect orders to review
PlanningExplode schedules and materials
RunCompare by resource
EvaluateAssess delivery feasibility
11 orders targeted for simulationDelivery feasibility95%Target profit82%
Capacity3 orders shippable from existing inventory
8 orders requiring production planning
2 overlapping production start dates
90%
Materials108 types of materials required
12 types to purchase
5 types with purchasing schedule issues
70%
People10 people requiredNothing to review
100%
Equipment5 required · 4 available1 piece of equipment under repair
80%

From the evaluation items, go directly to the production plan, material details, time and attendance data, and equipment schedule.Illustrative Example

APS operates on top of MPS and MRP

APS does not require new data. It makes assessments based on MPS schedules, MRP materials, CRP capacity, and time and attendance and equipment information when they are maintained on the same basis.

  • That is why the order mattersMPS and MRP automation comes first; APS is an extension that brings the results together.
  • Evaluations provide the basis for decisionsThe figures are calculated from the entered master data and plans; the final decision is made by the person in charge.

The evaluation items, calculation criteria, and scope of linked data are finalized after review with each customer.

CMC TECH · From Automated MPS and MRP to APS13 / 18
CMC-EIMS · Production Readiness13 · MES integration

Plans are validated on the shop floor,
and the shop floor improves the plans

The prepared plan is executed in MES, and the execution results flow back into planning. The gap between schedules on paper and actual shop-floor conditions is reduced only when equipment operation and workforce allocation are considered together.

Production PreparationMPS · E-MPS · MRP · CRP · APS
→
Production OrderSend only confirmed plans to the shop floor
→
→
Plan adjustmentReplanning based on actuals, work in progress, and losses
→
MES executionWork, inspection, and material consumption records

Three things MES returns to planning

  • InteractionInstructions, actuals, and work-in-progress status are exchanged between planning and the shop floor. This determines whether the next process can actually begin.
  • Error-proofingVerify at the time of work that materials or sequences different from the plan are not used.
  • TraceabilityRecord who made what, when, and under which LOT to track differences between the plan and execution.

The actual scope of data integration and level of automated control between planning and MES are confirmed during implementation.

CMC TECH · From Automated MPS and MRP to APS14 / 18
CMC-EIMS · Production Readiness14 · Change

When everyone sees the same plan
Their work changes

We do not promise implementation benefits in numbers. Instead, we explain what changes for each role. Actual results vary depending on the accuracy of master data and operating methods.

RoleNowAfter implementation
SalesWait for the production manager’s response before replying about the delivery dateRespond based on a schedule reviewed against capacity and materials
Production PlanningSplit the schedule in Excel and adjust it on the dayIdentify overload periods during planning and review again after changing the conditions
Purchasing · MaterialsDiscover shortages on the day and purchase again even when inventory is availableKnow in advance which weeks will have shortages and order only the actual shortfall
Shop floorReceive instructions but wait because materials, equipment, and personnel do not line upReceive instructions after readiness is confirmed, with actuals reflected in the next plan
ManagementIt is difficult to understand why the plan changedThe plan for each run, reasons for changes, and basis for purchasing remain documented

The calculation rules remain in the system even when the person in charge changes. However, BOMs, inventory, and expected receipts must be accurate, and production demand must be up to date to produce the same results.

CMC TECH · From Automated MPS and MRP to APS15 / 18
CMC-EIMS · Production Readiness15 · Implementation

Not everything at once
Expand step by stepdoes

Not every customer needs all five stages. We first review existing systems and master data, then configure the necessary stages first.

Master data refinementAlign items, BOMs, processes, resource capacity, and the factory calendar with actual shop-floor conditions.
MPS · MRP AutomationConnect orders to production instructions, and material requirements to purchase orders.
E-MPS · CRP expansionAdd process-level scheduling and reviews of equipment and workforce capacity.
APSExpand to delivery assessment by evaluating four resources together.

What to review together before implementation

  • Does the BOM match the materials actually consumed?
  • Can inventory quantities be trusted as the basis for calculation?
  • Are standard times and setup times managed for each process?

 

  • Who manages holidays and overtime, and where?
  • Are lead times, minimum lots, and order multiples defined for each item?
  • What data should be carried over from the existing ERP and MES?

The implementation period and cost are estimated after confirming the selected stages, data migration, integration with existing systems, and the scope of shop-floor application.

CMC TECH · From Automated MPS and MRP to APS16 / 18
CMC-EIMS · Production Readiness16 · Screens

Actual Program Screens

These are the MPS and MRP screens of CMC-EIMS. This material has been scaled down for public viewing, and the screens and scope to be implemented will be finalized after reviewing the business requirements.

MPS · Resource Utilization Status
MPS · Resource Utilization StatusLines with Concentrated Workloads and the Delivery Due-Date Baseline
MPS · Preview Before Confirmation
MPS · Preview Before ConfirmationSchedules Compared Against Capacity and Action Points
MPS · Separating Planning from Instructions
MPS · Separating Planning from InstructionsIssue Instructions Only Upon Confirmation
MRP · Weekly Requirements and Inventory
MRP · Weekly Requirements and InventoryIdentify the Weeks When Shortages Will Occur
MRP · Basis for Upper-Level Requirements
MRP · Basis for Upper-Level RequirementsTrace from Materials to Production Instructions
MRP · Firm Orders and the Confirmation Boundary
MRP · Firm Orders and the Confirmation BoundaryPlans That Remain in Place After Recalculation
CMC TECH · From Automated MPS and MRP to APS17 / 18
CMC-EIMS · Recommended Solution 02Next Steps

Production is decided before it begins.
We will prepare that decision together.

We begin by using one of your customer orders to verify together whether schedules, materials, and capacity remain connected under the same standards.

CMC TECH · From Automated MPS and MRP to APSThe figures in this proposal are illustrative examples.